In addition to developing the system, 597 bridge projects collected from Taiwan Area National Expressway Engineering Bureau were modeled and stored as a case base so that they can be used in the system. Interview and questionnaire were conducted to identify the influencing factors considered by the experts in determining the construction method for the bride upper structure. The weight of the factor was obtained using Analytical Hierarchical Process (AHP) method. For case-based reasoning, the factors areThe primary features of the system are as follows: (1) investigate the method and process that experts used for evaluating and selecting the construction method for bridge upper structure, (2) develop a casebase of the construction method for the bridge projects, (3) establish the similarity assessment model, and (4) develop the automated evaluation and selection system for bridge upper structure construction method using case-based reasoning.
|